Friday, 26 April 2013

Daimler Double-Decker 366 restoration update 1

In February 2013, we handed over a 1940s Coventry Transport Daimler double-decker to local bus enthusiast Roger Burdett, on a restoration loan.


This vehicle, original fleet number 366, was built to wartime austerity regulations, and as with many such buses, required extensive renovation after the war.  As such, it was re-bodied by Roe Bodies in 1951 and continued to be used by Coventry Corporation Transport for a number of years, before being donated to Coventry Transport Museum in 1971.

Inevitably for a vehicle that is over 70 years old, and has had this kind of life, the bus is now in need of major restoration – work that we as a museum do not currently have the resources to undertake.  So when we were approached by well-known bus enthusiast and collector Roger Burdett, with the offer of completely restoring ‘366’, we jumped at the proposition. 

At the time of the loan, our Curator of Vehicles Christiaan van Schaardenburgh said:

“We are a very small team looking after a collection of well over 200 vehicles, not to mention hundreds of cycles and motorcycles, and we would never have had the resources to give 366 the attention it needs.   We are therefore really thrilled that Roger is taking this project on, with a view to getting this delightful and popular vehicle back on the road.  We have known Roger for some time now, and as well as being a great friend of the Museum, we have seen his work on similar projects and we know that he’s going to do a great job on 366.”

And Roger said:

“I’m really looking forward to getting stuck into work on this fantastic bus – next year will mark 100 years since Coventry Transport first put motorised buses on the roads of Coventry, and my aim is to have 366 ready to take part in the centenary events for that anniversary.”

Roger has now had the bus for a few weeks, so we asked him to give us a rundown of how the work is going:
“Unfortunately the cold weather delayed work on the previous vehicle in the restoration pipeline, meaning that we were not able to start on 366 as soon as we would have liked, however I am pleased to say that we are now full steam ahead, spending around 50 hours per week on the vehicle.

The engine appears to be very sound, other than a cracked engine block.  To avoid a total engine strip down, we are going to remove the engine in June and then trial weld the crack at my premises, using skilled welders who currently work on the vehicles.  If this is not successful, the engine will need to go away to a specialist.

We have taken the panels off the rear end, revealing the modifications carried out when turning the vehicles back to a bus from a mobile workshop.  I am still looking for an ‘in service’ picture of the rear end of the vehicle before work can commence.
Rear end minus panels, clearly showing original window shape
The side panels below the downstairs windows will be off by the end of April and then we will see how the ‘wrong’ downstairs windows are fitted.  The frames that are currently on the vehicle are actually from a later bus, so we will have to make a major decision about whether to retain them or fabricate replica originals.


Offside minus some panels, showing wood frame in remarkable condition for 60 years old.
As regards the interior, we have examined the floors, which show some wear and cracking of the lino, but I feel that we can repair-paint and polish.  The seat frames are incorrect for the body (we can tell because the seat legs have been put on supports upstairs, rather than being bolted to the floor) - but we will not be replacing them.  The seat trip moquette is as used/very similar to London Transport (LT) RF and RT models.  I have clubbed together with a number of LT vehicle owners to have a new run of moquette made, and this is due for delivery in mid-May.  This will enable to seats to be re-trimmed, but with vynide borders, rather than the original unobtainable leather.

We are transferring destination blind mechanisms and blinds from Coventry 94.”


Downstairs saloon with seats removed.
Well done to Roger and his team for making a great start on this massive project – we will bring you further news of the restoration as the project develops.